December 9, 2024Eskom Marks 254 Days Without Load Shedding, Saving R17 Billion in Diesel Costs
Loading the Elevenlabs Text to Speech AudioNative Player...
Eskom has achieved a significant milestone, reaching 254 consecutive days without load shedding since March 26, 2024. This operational consistency has led to a year-on-year saving of nearly R17 billion in diesel costs, signaling major improvements in its generation capacity.
Key Achievements:
- Generation Recovery Plan: Structural improvements in coal-fired stations have bolstered reliability, with a focus on sustaining energy availability for economic growth and sustainability.
- Reduced Outages: Unplanned outages averaged 11,038 MW this past week, a marked improvement from 14,475 MW during the same period in 2023.
Energy Availability:
- Eskom’s Energy Availability Factor (EAF) averaged 59.4% over the past week and 62.8% year-to-date.
- Top-performing stations, including Majuba and Medupi, achieved EAFs exceeding 70%.
- An additional 2,600 MW is expected to come online by December 9.
Maintenance During Holidays:
With industries shutting down for the December holidays, Eskom plans to increase maintenance activities to further enhance fleet reliability.
Summer Outlook:
Eskom’s earlier forecast of a load-shedding-free summer, covering September 2024 to March 2025, remains on track due to these ongoing improvements.
This milestone highlights Eskom’s progress in stabilizing the grid, ensuring a steady power supply, and reducing reliance on costly diesel generators.